Mana College Refurbishment

Client: Ministry of Education
Location Mana College, Porirua
Consultants IR Group Ltd

As part of this extensive project, CCi striped-out much of the school’s Tech Block. This included work on: new lighting; new plumbing; new floor finishes; paint finishes; wall panels; new ceilings; and new and improved joinery. This included, installing external aluminium joinery to reinvigorate a science and IT area into a modern learning space, which features open plan teaching areas and upgraded bathrooms.

As the main contractor CCi were responsible for all the subcontractors.

The initial proposed scheme was heavily altered. This included adding a concrete deck and canopy, alongside further upgrades to exterior windows and entranceways.

This project was delivered over 26-week period, during which, CCi were able to incorporate a number of additional work scopes.

One of the challenges encountered during the project was the discovery of asbestos. In order to deal with this, CCi implemented our asbestos management plan. Another challenge CCi encountered were underground obstructions, which were discovered while excavating for new foundations. On identifying this, CCi ensured that the site was surveyed so that any unidentified obstructions were kept to a minimum. This also meant any resulting delays were also kept to a minimum.

During this project, CCi demonstrated that we manage all stakeholders’ expectations. This project was no different. Another consideration was to ensure we managed the students’ expectations while the works were carried out. We did this through using well fenced and hoarded barriers separating the site from the rest of the school. We also erected adequate signage and other warning systems to deal with school traffic and pedestrian flows.

Mana College is very happy with their new Tech Block, and was pleased that all stakeholders worked well together to identify and resolves and issues early on, efficiently and fairly.

Level 7 & 8 – 85 The Terrace

Client: Rapaki Property Group
Location Level 7 and Level 8, 85 The Terrace, Wellington
Architect Wright & Gray Architects Ltd

Having previously converted Level 3 at 85 the Terrace from tired building stock into a habitable, fresh and vibrant office space, the building owner had confidence in CCi and again asked us to convert a further two floors to house a tenancy for MSD.

MSD was faced with the challenge of finding alternate tenancy space after the Kaikoura earthquake and had strict occupation dates. CCi came on board early, during the negotiation phase, and provided valuable feasibility and construction advice. This ensured both MSD and the landlord could proceed with the project in confidence.

This fitout was custom-designed to suit MSD requirements. CCi worked with: the landlord’s Architect; MSD’s Architectural Advisor; the building owner; and other key MSD stakeholders. This ensured we were able to manage the landlord’s expectations, while also following the tenant’s specific brief. MSD had high specification details that required thought and careful planning. This included: acoustic rated walls; new security systems; corporate design requirements; and feature lift lobby linings. CCi also co-coordinated PS1 designs for seismic wall and ceiling bracing and worked with the tenants’ nominated contractors to meet their technology needs.

The solution to meet the specified time-constraints was to run a combined landlord basebuild and MCHF. Work ran to a tight schedule, with floors handed over a month apart. Stage One had a programme of just eight weeks, which also included design of the mechanical ventilation system.

This has only been achieved by working on both floors at the same time, monitoring the site on a day-by-day basis (sometimes hour-by-hour) and making timely request for information from the project team and the City Council. 

A great rapport was developed between the project team and any technical questions or construction queries were handled efficiently and effectively. The finished fit-out is quiet, comfortable and modern and both the landlord and tenant are very happy with the space created. 

Barnardos Childcare Facility

Client: The Wellington Jewish Community Centre and Barnardos
Location 74-90 Webb Street, Te Aro, Wellington
Consultants Covekinlock New Zealand Ltd
Architect Craig Fafeita

CCi was approached to assist with this project on a negotiated basis, with Stimpson & Co, Craig Fafieta Architect and Impact Project Management.

This project involved an internal strip out of a large part of the ground floor at The Wellington Jewish Community Centre (basebuild), which we converted this  into a new childcare facility for Barnardos. It comprised of: an “under twos” section at one end, including sleep rooms; a common central area, comprising of offices; kitchen and bathroom facilities; and an “over twos” area at the other end. This last part includes sleep rooms that can be opened out to access the big outside play area, through newly created exterior aluminium doors.

This project required CCi to install services to meet the needs of the childcare facility. This included: new water and waste services; electrical and data reticulation; heating; and ventilation.

This project had some budget constraints. To facilitate this, CCi ensured staff worked with the project team to provide timely advice on the cost implications. This meant that both The Wellington Jewish Community Centre and Barnardos could make informed commercial decisions.

WEGC – He Haurahi Tamariki Remediation Project

Client: MoE - Wellington East Girls College
Location 9 Matai St, Tawa, Wellington
Consultants Covekinlock New Zealand Ltd
Architect McKenzie Higham Architects

CCi were approached to price this project, via an Early Contractor Engagement process. After several rounds of budgeting and feasibility analysis the project was given the green light by MOE.

The agreed scope of works was targeted improvements to the cladding and substructure in localised areas, to provide remediation solutions for issues caused by water ingress and black mould. To ensure this was achieved successfully, the monolithic cladding was removed and replaced with weatherboards on a cavity batten system and the flashing system improved. Sections of framing were replaced, and some walls were rebuilt. The retained timber structure was treated with Framesaver (a treatment preservative).

Keeping to programme was of utmost importance because the school needed to move back in over the term break. To facilitate that, CCi accelerated the works twice. Firstly, to mitigate a two-week delay due to a delayed building consent issue, and secondly, to incorporate additional work areas identified by the building surveyor. Multiple work faces were opened, meaning that at its peak, three labour crews were engaged to resource the project in order to meet the deadlines.

CCi employed two further strategies to ensure re-occupation at the nominated time:

  • Work elements were rescheduled so that any tasks which had potential to take longer than planned, were restricted to areas of the school which would not be habited by students i.e. painting the weatherboards in the back section in a fenced-off area; and
  • CCi applied shrink-wrap, and also built enclosed scaffold structures at workfaces that were most at risk of delays due to weather. These areas were monitored a daily basis.

CCi devised a concise programme and work sequence. CCi’s Site Manager kept in constant contact with the Project Team consultants and was well aware of any detail change or deviation. This prompt action and reaction to any site queries kept momentum going and minimised delays at hold points.

The positive professional relationship between CCi and the project team members lead to open debate of issues, sensible and cost-effective determinations of solutions and prompt financial decision making. Behind the scenes, the project team had: confidence in CCi’s ability to make quick decisions; CCi’s ability to respond quickly to site queries; and provision of financial updates, which influenced the project scope.

CCi completed the project QA checklist and liaised directly with the surveyor regarding the extent of remediation work and quality of the installed detail. To ensure efficiency, documentation was signed off as work was completed, then compiled into a master document and submitted at completion.

Due to the attention to detail; clever programming; and the commitment of everyone involved - including the contractors - to meet the deadline, the project was handed over at the agreed date and within budget. The project exceeded MOE’s and the school users’ expectations.

Most crucially MOE commented that CCi were completely on board with the deliverables of the project and actively worked with the school to accomplish all requirements of the project.

Innovations on this project:

  • The old sandpit sand was recycled into the basecourse of landscaping siteworks instead of going to landfill;
  • Salvaged carpet was placed on the roof to protect surfaces at work zones, reducing construction waste;
  • Responsibility for photographing construction details was delegated to the carpenters, who used a site camera. This gave the carpenters ownership and a sense of pride in the work, and increased engagement, whilst at the same time increasing accountability for workmanship;
  • Through the sharing aspect of the Procore software management tool, project team members, and any other stakeholders, had real time access to photos, project updates and the ability to transfer documents in timely and effective manner;
  • The weatherboard was ordered form the factory with the first paint finish coat already applied;
  • Weather-related disruptions and delays; were minimised through the use of stratigised shrink-wrap; and
  • WCC Inspections were scheduled early and to occur on a weekly basis so that critical milestones were met.