| Client: | The Wellington Jewish Community Centre and Barnardos |
| Location | 74-90 Webb Street, Te Aro, Wellington |
| Consultants | Covekinlock New Zealand Ltd |
| Architect | Craig Fafeita |
CCi was approached to assist with this project on a negotiated basis, with Stimpson & Co, Craig Fafieta Architect and Impact Project Management.
This project involved an internal strip out of a large part of the ground floor at The Wellington Jewish Community Centre (basebuild), which we converted this into a new childcare facility for Barnardos. It comprised of: an “under twos” section at one end, including sleep rooms; a common central area, comprising of offices; kitchen and bathroom facilities; and an “over twos” area at the other end. This last part includes sleep rooms that can be opened out to access the big outside play area, through newly created exterior aluminium doors.
This project required CCi to install services to meet the needs of the childcare facility. This included: new water and waste services; electrical and data reticulation; heating; and ventilation.
This project had some budget constraints. To facilitate this, CCi ensured staff worked with the project team to provide timely advice on the cost implications. This meant that both The Wellington Jewish Community Centre and Barnardos could make informed commercial decisions.